anyone pls let me know ehn when TECO is done in SAP Ps
Comments
03 Aug 2009 6:10 am Guest
TECO set on any WBS when project is technically completed no external cost will come on that project.
other reason is that teco can be set ,when we want to track the actual cost on the project and want to restrict any one to book the external cost on that project for specific timeline.
THanks
Sunil
13 Mar 2010 4:05 am Guest
How to teco the project .
Please provid steps
24 Dec 2010 9:54 am Guest
Steps to set TECO
If you have access to CJ20N
The TECO can be set on the Activity element Netework or at WBS level
at Menu go to Edit> Status > Complete Technically > Set
19 Jul 2011 12:41 pm Arsene MBITY
And TECO can set only at the network or the activity